Chapter 2: Server Installation
2-5
Figure 2-1. Installing Chassis Rails
Installing the Server into the Rack
The next step is to install the server into the rack. Do this by lining up the rear
of the chassis rails with the front of the rack rails. Slide the chassis rails into the
rack rails, keeping the pressure even on both sides (you may have to depress the
locking tabs when inserting). See Figure 2-2.
When the server has been pushed completely into the rack, you should hear the
locking tabs "click". Finish by inserting and tightening the thumbscrews that hold
the front of the server to the rack.